Looking Good
27/01/12 16:43
Outside
The outside has been tidied up now and new paths around the building are complete. The ground has been reinstated and it is starting to look less like a building site and more like a touring park again! And what a stunning January day we have had today!
The outside has been tidied up now and new paths around the building are complete. The ground has been reinstated and it is starting to look less like a building site and more like a touring park again! And what a stunning January day we have had today!

Inside
Alan and Mike have been painstakingly applying 2 coats of Danish Oil to an extraordinary quantity of Cedar cladding ready for Oggy and Rich to get busy on the internal transformation. We have Cedar lined the underside of the Gents roof, which gives an idea of how the inside will look when complete.



Scaffold Gone
07/01/12 17:49
The render is finished and the scaffold has been removed from our new toilet and shower building. Starting to look finished from the outside!

We have now started the internal fit out. One week in and we have made a big impression!

New Toilet Block Update
18/12/11 11:31
The shell is almost complete! The plasterers are waiting for a couple of days good weather in which to render the exterior block work, then the scaffold can come down.

The floor screed has been laid and the external doors have been hung!

Build Progress
23/11/11 13:51
The blockwork is almost finished and work has started on constructing the roof of our new amenity building.

Lots of Blocks
13/11/11 11:12
The builders have made good progress this week. Just hoping the weather remains good.